Breaks Fold Farm, 26 August 2026

Image
We've had a good summer for walling, despite the heat, and this week was one of the best.  The threatened rain didn't materialise and instead we had a warm and pleasant day.  The six  of us Barry, Andy, Duncan, Simon, Rod and Graham worked on some 30 yards of wall.  Andy and Graham, and Simon and Duncan continued on the first fifteen yards, bringing it nearly to coverband level while Rod worked on twelve yards of retained wall lowering it in places and generally fixing it ready for toppers. Barry was at the far end, working all alone!, adding four courses to both sides of a two yard gap. Good progress was made,, but we're currently going through a phase where finding the right stone is really hard work.  This was made up for by a  visit from Liz and, even more so, when Paul and Amanda, who live nearby, walked past and told us what a magnificent wall it was; it's nice to get such praise every now and again. This was our tenth week on site this year, and by n...

St Cuthbert's playing field, Pateley Bridge 19 August 2026

Image
  A split team this week to knock off two outstanding jobs. Andy, Rod & Barry to Pateley to repair a gap in the school playing field wall, probably pushed through by grazing cattle on the other side. Some preliminary work with shears and a sickle exposed the fallen stone and we were pleased to find fairly secure ends to which we could rebuild, and the foundations appeared sufficiently strong without the need to take down to that level. A very convenient pile of surplus stone nearby supplemented the provision and steady progress was made in warm sunshine during the morning. The forecast showers held off until grey clouds loomed over Greenhow and an early lunch was taken under the shelter of an oak tree while the rain passed through. The wall was completed with a satisfying run of top stones, and a finish at 2.30pm.

Timble Grange Bio Hub 19 August 2026

Image
Three wallers , Duncan, Simon and Rob went to finish off the job at the Bio-hub site at Timble, mostly completed in October and November of the previous year.  Duncan used his charm and kind lady along the lane allowed them to park their two cars in front of her house.  We started by removing the foundation stones ready for use later.  We missed having the mattock and big bar available but we managed eventually.  Having laid the first three courses all the decent stone had been used.  We managed to uncover some that had disappeared under the grass but decided to lower the height of the wall to match the other side of the gatepost.  Toppers were non existent so we used the largest stones we could find from the reject pile and stole a couple from further down the wall.                                                 ...

Breaks Fold Farm, 12 August 2026

Image
  A mighty crew of eight of us at Breaks Fold Farm;  Andy, Barry, Dave, Duncan, Rob, Simon, Wayne and Graham.  A pleasant but warm morning with the sight of heather in the distance and the occasional flock of geese and the odd kite flying above. Unusually there was a steady stream of aircraft flying into Leeds/Bradford, obviously a factor of the wind direction.  Up to lunchtime good progress was made, but during the break someone switched the heater on and by 14.30 any energy had been sapped away.  From the off, Barry and Graham detached themselves and worked on the next stretch. For a good length, the wall was in relatively good condition so only toppers and a course were removed to lower the wall to match what the rest of the team were working on. They then set about dismantling a three yard stretch which needed a rebuild.  By lunchtime the wall had been cleared and half the foundations added. The afternoon was another story. Barry completed his foundatio...

Breaks Fold Farm, 5 August 2026

Image
  Our 8th week at Breaks Fold Farm and a further 5 yards of old wall dismantled to a point where the next section of the original may be good enough to preserve. Simon & Barry took on this work while Andy, Dave, Duncan & Rod completed foundations and added courses to the 10-yard working stint. Windswept showers kept us cool with fleeces donned for most of the day, a striking contrast to the calm and warm conditions in July. The Knabbs Ridge turbines were in continuous steady rotation all day. At end of play, Simon & Barry had set foundations and added a course to their 5 yard section; Andy, Dave, Duncan & Rod laid three courses over foundations on their 10-yards. Another productive day with a 3.15pm  finish.                       Early afternoon: team on the job                                 ...