Breaks Fold Farm, 1 July 2026
Seven wallers gathered at Breaks Fold Farm on a calm, warm morning. The lines were set on the working stint while Dave, Rob & Simon began dismantling the next 10m section. Andy, Barry, Duncan & Rod continued the build which was raised by another 5 courses by the end of the day, much of the stone needing hammer work. The dismantlers having set out the stones very tidily, then put in very substantial foundations with a satisfying completion by the 3pm finish.